Last updated: November 10, 2026

A concrete encased duct bank is a group of ducts held on spacers and surrounded by concrete. The concrete is mechanical protection and position control. It is not the part that gets tested.
Alberta’s governing specifications set the duct size, the spacer centres, the concrete class, the cover and the pull rope. Then they accept the finished work by pulling a mandrel through each duct. Nothing in the acceptance test measures the concrete.
That gap is the whole subject of this article.
What the concrete is doing
Four jobs. No more.
| Job | What it means |
|---|---|
| Mechanical protection | The encasement takes impact and point load so the duct wall does not have to |
| Position control | Ducts stay on their centres, at grade, for the life of the run |
| Cover reduction | Encasement is the recognised way to protect a raceway where cover alone is not available |
| Load path | A bank under a roadway, pad or track carries traffic load across the ducts |
The concrete does not carry the cable. It does not keep water out of the duct. Joints do that.
The Alberta specification that names numbers
Alberta Transportation Specification 2.21, Cable Ducts, is the clearest set of numbers in the province for this work. It is written for cast in place encasement on a highway contract, and it is the document most Alberta specifiers borrow from.
| Item | Requirement |
|---|---|
| Duct | 100 mm nominal inside diameter, rigid non metallic PVC, matched couplings |
| Spacers | Cast concrete or interlocking plastic, 100 mm duct on 200 mm by 200 mm centres |
| Spacer materials prohibited | Wood and metal |
| Concrete strength | Minimum 20 MPa compressive at 28 days |
| Maximum aggregate | 19 mm |
| Cement | Type V sulphate resistant portland cement |
| Maximum slump | 80 mm |
| Air content | 5 to 7 percent, air entraining admixture required |
| Cover | Ducts at least 600 mm below subgrade |
| Coupling stagger | At least 150 mm along the run |
| Pull rope | 7 mm nylon cord, continuous, 3 m spare at each end |
| Marker | 50 mm by 100 mm red painted marker from the duct entrance to 450 mm above grade |
| Payment | Per metre of encasement, including two 100 mm ducts |
Two more numbers sit around the bank rather than in it. Where soft ground is found, the trench is undercut at least 150 mm, replaced with acceptable material and compacted to 95 percent Standard Proctor Maximum Dry Density. At each duct end, a sand envelope extends 1 m from the duct, 600 mm wide, from the bottom of the duct system to 500 mm above the top duct.
The specification also sets the concrete testing: air content to ASTM C231, slump to ASTM C143, and compressive strength to ASTM C31 and C39, one test of each per pour day, with each strength test made from two standard specimens.
The spec prescribes the concrete and accepts the duct
Read the acceptance clause and the frame becomes obvious.
Final acceptance under Specification 2.21 is a mandrel drawn through each individual duct, in the Consultant’s presence, after the concrete has set. Any duct that fails is cleared or replaced. Only once every duct is certified clear is the run accepted and the ends sealed.
So the materials are prescriptive and the acceptance is performance based, and they do not test the same thing.
| Controlled by the spec | Tested at acceptance |
|---|---|
| Concrete strength, slump, air, aggregate, cement type | Nothing |
| Spacer type and centres | Indirectly, through duct alignment |
| Cover and grade | No |
| Joint watertightness | Indirectly, through debris in the duct |
| Duct bore, clear and continuous | Yes, directly, duct by duct |
A bank can pass every cylinder break on the project and still be rejected. The concrete is the easy part to get right and the only part that is written down in detail.
Why ducts fail during the pour
The Alberta Bridge Construction Inspection Manual is blunt about the failure modes, because the inspector is the person who has to catch them. Section 11, Service Ducts and Voids, names two.
Flotation. Ducts and voids are buoyant during concrete placement and tend to float up. They must be tied down by an approved method. Specification 2.21 says the same thing in its own words: anchor the duct assembly to the trench bottom so it cannot shift or float during the pour.
Mortar in the joint. Mortar leaking into a joint can block the conduit and make it impossible to pull wires through later. The fix is upstream of the pour, in joint preparation and in wrapping any split duct so concrete cannot enter.
The manual adds the checks that follow from those two: conduit continuous and bent in standard benders, expansion devices at movement joints, pull wire installed and observed, blockages cleared to the Bridge Project Engineer’s satisfaction, and the buried ends located and recorded on the as constructed drawings.
Placement method is specified for the same reason. Specification 2.21 requires concrete to be chuted down the sides of the bank so it flows under and up around the ducts, then rodded with a flat bar. The point is to fill the space beneath each duct without lifting the array.
Cover: the number depends on which document governs
There is no single Alberta cover number for a duct bank, and specifiers who assume there is get caught.
On an Alberta Transportation contract, the figure is explicit: at least 600 mm below subgrade.
On a building or site electrical installation, cover comes from the Canadian Electrical Code, Part I. Alberta declared CSA C22.1-24, the 26th Edition, in force on April 1, 2025, replacing CSA C22.1-21, which had been in force since February 1, 2022. The Code sets minimum depth of burial by table rather than by a single value, and the required cover changes with voltage, with location, and with whether the run is direct buried, in a raceway, or encased. Confirm the governing row for your circuit and your location against the current edition rather than carrying a number across from a highway specification.
A utility owned run adds a third document, because the utility’s own standard governs its side of the connection. The split between the utility’s scope and yours is the same question we worked through for precast transformer pads, and it is worth settling before the duct bank is drawn, not after.
Where a precast unit changes the risk list
Specification 2.21 is a field cast procedure. Every clause in it is a field risk. A precast duct bank section, cable trough or utility trench moves most of that risk into the plant.
| Field cast risk | What precast changes |
|---|---|
| Ducts float during placement | Duct positions are cast and cured before the unit leaves the plant |
| Mortar enters a joint | Bores are formed and inspected under plant conditions |
| Spacer centres drift | Centres are fixed by the form, not by strapping in a trench |
| 28 day wait before acceptance | Units arrive at strength; the field work is setting and jointing |
| Concrete tested per pour day in the trench | Plant quality control covers the concrete before delivery |
| Weather window on the pour | Setting a unit is a shorter exposure than a trench pour |
What does not change: cover, grade, bedding, joint integrity, the pull rope and the mandrel. Those are still field work, and the mandrel still decides acceptance.
The product family is established. The National Precast Concrete Association lists utility trenches, utility vaults, manholes, pull and splice boxes, equipment pads and enclosures as standard underground precast, and names ASTM C857 for minimum structural design loading, C858 as the product specification, C891 for installation and C1037 for inspection of underground precast concrete utility structures. Load rating is the question most often asked late and it is a design input, not a finish option, which is why we set it out separately for utility vaults and manholes.
A linear buried unit behaves much like a precast trench drain from a handling and jointing point of view, even though the service inside is different.
Ordering: what the plant needs
Send these and a duct bank quote is a day’s work rather than a conversation.
- Duct count and size. Nominal inside diameter and the number of ducts, including spares.
- Array geometry. Rows and columns, and the centre to centre spacing required by the governing specification.
- Encasement envelope. Concrete cover required around the outside duct, or the overall section dimensions if the design is already fixed.
- Run length and layout. Total metres, plus any bends, with the minimum bend radius the cable allows.
- End conditions. What the run terminates into at each end: a vault, a pull box, a pad, a building wall, or existing conduit, and the coupling type needed.
- Cover and loading. Depth to finished grade and what travels over the bank: landscaping, light vehicle, highway loading, or track.
- Governing specification. Name it. Alberta Transportation Specification 2.21, a municipal standard, a utility standard or a project specification each produce a different unit.
- Concrete requirements. Strength, cement type and exposure class if the project specification differs from the default.
- Site access and setting. Crane or excavator reach, trench width available, and whether units can be set the day they arrive.
- Delivery date. The date the trench is open, not the date the drawings are issued.
Drawings and lead time for buried structural units start on our precast solutions page. Send the duct array and the governing specification with the request and we will quote the unit, the jointing and the delivery sequence together.
FAQ
Is a precast duct bank accepted the same way as a cast in place one? The mandrel test is a duct test, so it applies either way. What changes is how many ways the duct can be damaged before the test.
Can the encasement be unreinforced? That is a design decision set by the loading over the bank and the governing specification. Specification 2.21 lists a welded wire reinforcement standard among its concrete references, which tells you reinforcement is contemplated rather than assumed.
Why sulphate resistant cement? Specification 2.21 calls for Type V portland cement. Buried concrete in parts of Alberta sits in sulphate bearing soil, and sulphate attack is a durability problem that the mix, not the geometry, has to answer.
What is the pull rope for if the cable is not installed yet? It is the only practical way to pull cable later, and it is also the first evidence that the bore is clear. Specification 2.21 requires it continuous, checked for kinks and joints, with spare coiled at each end.
Do we still need markers over a precast bank? Yes. Marking a buried raceway is a Code obligation and a locate obligation, and it is independent of how the encasement was built.
Can one bank carry power and communications? Separation between services is a Code and utility standard question, and it is decided before the array geometry is fixed. Ask it early, because it changes the number of ducts and therefore the unit.
Where this article stops
This article covers the concrete encasement of cable ducts in Alberta: what the governing specifications require of the concrete, the spacers, the cover and the pull rope, how the work is accepted, and what a precast unit changes about the risk list.
It does not size cable, set ampacity, or decide derating for ducts in concrete. Encasement affects the thermal environment of a conductor, and that calculation belongs to the electrical designer.
It does not give the Code cover value for your run. That comes from the current edition of the Canadian Electrical Code and from the authority having jurisdiction.
It does not cover the vaults, pull boxes and equipment pads that terminate a duct bank, beyond naming them. Those are separate units with their own load ratings and their own ordering information.
It does not cover electrical grounding and bonding inside the bank.
Sources
- Specification 2.21, Cable Ducts, Alberta Transportation
- Bridge Construction Inspection Manual, Section 11: Service Ducts and Voids, Alberta Transportation
- Electrical codes and standards, Government of Alberta
- Underground utility products, National Precast Concrete Association