A waste enclosure is a pad, three or four walls, a gate opening and bollards. It is the simplest structure on most sites.
It is also the structure most often drawn last, at whatever size is left over after parking.
That is the wrong order. The governing design standard in Alberta’s largest municipal waste system dimensions almost nothing about the enclosure itself. It dimensions the containers inside it, the space around each container, and the envelope the collection vehicle needs to reach it. The enclosure is a derived number.
This article sets out which numbers are published, which are not, and what a precast unit changes.
What the standard dimensions, and what it leaves to you
The City of Calgary Design Standards for the Storage and Collection of Waste, DPS-STDRD-0002, is the most detailed public document of its kind in the province. Read it looking for enclosure dimensions and the result is surprising.
| Published in the standard | Not published in the standard |
| Weekly waste volume per dwelling unit | Enclosure interior length or width |
| Clear space required around each container | Wall height |
| Minimum weight capacity of the collection area | Gate leaf width |
| Collection route width and height clearance | Pad thickness or reinforcement |
| Overhead and side clearance at the collection point | Setback from the property line |
| Maximum grade across the storage and collection area | Drainage treatment inside the enclosure |
Everything in the left column is a constraint you must satisfy. Everything in the right column is a decision you make, and then defend at review.
Sizing the inside: a volume calculation, not a drawing
The standard does not tell you how big the enclosure is. It tells you how much waste the site generates, and leaves you to fit containers around that number.
| Development type | Weekly volume basis |
| Multi-family | 0.24 m3, or 0.3 cubic yards, per dwelling unit, multiplied by the number of dwelling units |
| Commercial strip mall | 1 m3 per bay, average week |
| Other developments | 3 m3 per 1000 m2 of development, average week |
| ICI basis of calculation | The greater of the per-bay and per-area figures |
| Restaurant grease waste | An additional storage area of 1.5 m by 2.0 m |
Two consequences follow immediately.
A sixty unit building generates a little over fourteen cubic metres a week on that basis. That is not one bin. It is a bank of them, and the bank, plus the clear space the standard requires around each unit, is the floor area the enclosure has to hold.
The restaurant grease allowance is separate space, not shared space. A food service tenant adds a dedicated three square metre area to the enclosure or beside it. If that waste is going to an interceptor rather than a drum, the sizing question moves to a different document, and we set that one out in precast grease interceptors in Alberta.
The clearances that set the footprint
Container space is not container footprint. The standard requires working room, and it requires it in every direction.
| Requirement | Value |
| Accessibility space around each container | 0.5 m in all directions |
| Manoeuvring space from storage to staging and collection | 0.5 m in all directions |
| Maximum grade where containers are stored, manoeuvred or collected | 2 per cent in all directions |
| Minimum weight capacity of the collection area | 25,000 kg |
| Automated container storage, per dwelling unit, on private property | 2.1 m by 0.8 m |
The 0.5 m figure appears in both the multi-family and the ICI sections of the standard, with the same wording. It is not a rounding allowance. On a four bin enclosure it is the difference between a unit that clears review and one that does not.
The 2 per cent maximum grade is the clause that most often forces a change to the site plan rather than to the enclosure. It applies in all directions, across the storage area and the collection area, and it has to coexist with whatever the site needs to do with surface water.
The collection vehicle is the governing dimension
Here is the part that is routinely missed. The largest dimensions in the standard are not the enclosure’s. They belong to a truck that is on site for four minutes a week.
| Dimension | Requirement |
| Collection route minimum drivable width | 5.0 m |
| Collection route height clearance above the driving surface | 5.0 m |
| Overhead clearance at collection areas | 6.8 m |
| Side clearance at collection areas | 1.0 m on either side of the vehicle |
| Pavement weight capacity: pads, aprons, approach, parking structures | 25,000 kg |
| Minimum distance from a dead end road to the last container’s collection point | 7.0 m |
| Maximum reverse movement | Two truck lengths |
The City’s own specification drawings add the figure that decides many site layouts: the front end loader requires a minimum turning radius of 12.8 m. The same drawings call for a minimum 6.8 m dumping clearance, which is the standard’s overhead number confirmed from a second document, and a minimum 5.0 m for manoeuvring.
Read those two lists together and the frame is clear. The enclosure can be perfectly sized and still be unservable, because the thing that has to reach it needs a 12.8 m turning radius, 6.8 m of air above it, and pavement rated for 25,000 kg all the way in.
Pavement capacity is a structural requirement, not a surfacing choice. A 25,000 kg vehicle tracking the same path weekly is a fatigue load on an approach and a point load on a pad, which is the same problem we work through for precast concrete pavement panels in Alberta.
The enclosure dimensions that are published
The standard is quiet on enclosure geometry. The specification drawings are not. These are the only published hard numbers for the structure itself.
| Element | Requirement |
| Minimum clear opening | 3.0 m |
| Overhead door | 3.0 m by 2.1 m |
| Minimum overhead door height, where noted | 1.80 m |
| Bollard clear opening | 3.0 m by 1.2 m |
| Bollard offset from the wall | Maximum 0.1 m |
| Bollard embedment | 1.0 m below grade |
| Concrete curb and wheel stops | Minimum 0.3 m tall and 0.2 m wide |
| Maximum slope from the rear of the enclosure to the road or parking lot | 2 per cent |
The 3.0 m clear opening is the controlling number for a precast unit, because it sets the span of the opening in the front wall and therefore the reinforcement above it. A 3.0 m clear opening is not a 3.0 m gate. Gate hardware, bollards set no more than 0.1 m off the wall, and the door frame all live inside or beside that dimension.
Bollard embedment of 1.0 m below grade matters to the pad detail. A bollard that deep is not set in the enclosure slab. It is set through it or beside it, and that is a decision made at the plant, not on site.
Containers: one dimension is fixed, the rest is not
Specifiers often want a container schedule. The public documents support part of one.
The City’s commercial bin dimensions sheet and the specification drawings agree on width: every bin size from two to eight cubic yards is 2.03 m, or 6 feet 8 inches, wide. That number is reliable because two independent City documents print it.
Depth and height are a different story. The two documents give different figures for the same nominal capacities, and the specification drawings carry an explicit note that container dimensions may vary between companies. Capacities run from two cubic yards, about 1.5 m3, to eight cubic yards, about 6.1 m3.
So the design rule is: fix the width at 2.03 m per bin position, confirm depth and height against the hauler who will actually service the site, and add the standard’s 0.5 m clear space on every side. Do not design the enclosure depth from a published bin table.
Three gates, and none of them is the plant
The approval structure is worth stating plainly, because it is commonly collapsed into one step.
A Waste and Recycling Services specialist reviews the planning application and provides written comments on whether the minimum design requirements are included or could be met. That review does not approve the application.
The City’s Development Authority approves the application and issues the planning permit.
Planning approval does not automatically qualify the site for City waste collection. That is a separate application.
A site can therefore hold a valid permit, with a compliant enclosure built to the standard, and still not be on a City collection route. The enclosure is correct; the service agreement is a different file. Confirm which gate your project has cleared before the enclosure is fabricated, because a private hauler’s vehicle envelope may not match the City’s.
What precast changes
| Site built enclosure | What precast changes |
| Opening span formed and reinforced in the field | Opening span and lintel reinforcement cast to the 3.0 m clear dimension in the plant |
| Wall thickness and finish vary with crew and weather | Panel thickness and finish controlled under plant conditions |
| Pad poured, cured, then loaded by a 25,000 kg vehicle | Pad and walls arrive at strength; exposure to an early load is shorter |
| Impact damage repaired in place, repeatedly | Damaged panels are replaceable units |
| Enclosure built after paving, around parked cars | Set in one visit, usually in a single morning |
| Seasonal shutdown on a late pour | Setting a unit is a short weather window |
What precast does not change: the volume calculation, the 0.5 m clear spaces, the 2 per cent grade, the 25,000 kg pavement capacity, the vehicle envelope, and the review. Those are site decisions and they are made before a unit is ordered.
Enclosure walls that also retain grade are a different design problem, and the acceptance criteria shift accordingly. We set those out for precast retaining walls in Alberta.
Ordering: what the plant needs
- Dwelling unit count, or development area and bay count. This produces the weekly volume and therefore the bin count.
- Bin schedule. Number of containers, nominal capacity, and the hauler’s confirmed depth and height for each.
- Interior clear dimensions. Bin positions plus 0.5 m on all sides, stated as a clear interior length and width.
- Opening. Clear opening width, gate type, and whether an overhead door is required.
- Wall height and configuration. Three walls or four, screening height required by the municipality, and any grade retained by a wall.
- Pad requirement. Whether the pad is in our scope, and the vehicle weight the approach and pad must carry.
- Bollard layout. Positions, offset from the wall, and embedment depth.
- Grade and drainage. Finished grades at all four corners, and where surface water leaves the enclosure.
- Governing documents. The municipal waste design standard and the land use or zoning requirement for screening. Each produces a different unit.
- Access and setting. Crane or picker reach, headroom at the setting location, and whether the pad is ready.
- Delivery date. The date the pad and approach can take a truck, not the date the permit was issued.
Drawings and lead times for site structures start on our precast solutions page. Send the unit count and the bin schedule with the request and we will quote the enclosure, the pad detail and the setting sequence together.
FAQ
How big does a waste enclosure have to be? The standard gives no enclosure dimension. It gives a weekly volume per dwelling unit or per unit of development area, and 0.5 m of clear space around every container. The interior size is the result.
Does the enclosure have to be concrete? The design standard regulates clearances, grade and weight capacity, not wall material. Screening material is usually set by the municipality’s land use or zoning requirement. Concrete is chosen for impact resistance at the opening, where bins and vehicles make contact weekly.
What is the 6.8 m clearance for? It is dumping clearance. A front end loader lifts the container over the cab to empty it, so the air above the collection point governs, not the air above the enclosure walls.
Can the enclosure sit on a parking structure? Only if the deck carries the collection vehicle. The standard applies the 25,000 kg capacity to pads, aprons, approaches and parking structures alike.
Why does the opening matter more than the walls? Because it is the only dimension published for the structure, it sets the lintel span, and it takes every impact. Three metres clear with bollards no more than 0.1 m off the wall is a tighter detail than it looks on a plan.
Do these numbers apply across Alberta? They are the Calgary standard. Other municipalities publish their own, and a private hauler’s vehicle may need different clearances. Name the governing document on the drawing set.
Where this article stops
This article covers the dimensional and loading requirements that drive a waste and recycling enclosure on an Alberta multi-family or ICI site, what the published design standard does and does not specify, and what a precast enclosure changes about the build.
It does not set screening height, materials or architectural treatment. Those come from the municipal land use or zoning bylaw and from the development permit conditions.
It does not size an interceptor, a drain or any plumbing inside the enclosure.
It does not design the pad, the approach structure or the parking deck beneath it. The 25,000 kg capacity is a design input for that work, not the design.
It does not decide whether a site qualifies for municipal collection. That is a separate application to the municipality.
Sources
- Design Standards for the Storage and Collection of Waste, DPS-STDRD-0002, City of Calgary Waste and Recycling Services
- Waste and Recycling Services specification drawings, City of Calgary
- Commercial bin dimensions, City of Calgary