Last updated: November 15, 2026

Acceptance is an event, not an opinion. It happens at the trailer. The standard guide specification for plant-precast products puts it in one line: on delivery to the jobsite, all precast units are inspected by the customer or the customer’s agent for quality and final acceptance (NPCA General Guide Specifications, clause 1.6.3).
The next clause is the one that costs money. Once the customer or the customer’s agent accepts the product, the manufacturer is no longer responsible for product damaged by improper jobsite handling (clause 1.6.4). Signing moves the handling ledger across the fence.
So the inspection is not a formality. This article sets out what to look at, which defects are plant problems and which are site problems, the thresholds that force an engineer into the decision, and what the plant needs.
The three outcomes, and nothing in between
Every non-conformance resolves into one of three results. Accept as is. Accept with repair. Reject.
PCI Northeast’s guidelines for resolving non-conformances sort defects into repairable and non-repairable. Repairable defects come from manufacture or mishandling; minor ones are repaired at the plant, or at the project site when shipping or erection caused them. Non-repairable non-conformances may be grounds for rejection of the element.
Two cases drive rejection in that document. A major defect affecting structural integrity or durability. And a significant pattern of repairable defects, which points at process control rather than at one bad unit. The second case is the one GCs miss. Three identical chips on three units is a different conversation from one chip on one unit.
| Outcome | Trigger | Who closes it |
|---|---|---|
| Accept as is | Defect does not impair functional use or expected life | Customer or customer’s agent at delivery |
| Accept with repair, minor | Cosmetic or shallow damage, pre-approved procedure exists | Producer QC with owner’s representative |
| Accept with repair, major | Defect impairs functional use or expected life | Owner or owner’s representative, engineer of record where capacity is touched |
| Reject | Non-repairable, or a pattern indicating process control failure | Owner or owner’s representative |
Minor and major are defined terms, not adjectives
The split is written down. It is not a judgment call made at the trailer.
Under the guide specification, defects that will not impair the functional use or expected life of a precast unit may be repaired by any method that does not impair the product (clause 2.3.4.6.1). Defects that do impair functional use or expected life are major: they must be evaluated by qualified personnel to decide whether repair is feasible, and final acceptance of a major defect repair is by the owner or the owner’s representative (clause 2.3.4.6.3).
That second sentence settles the most common site argument. A producer cannot sign off its own major repair. The owner side signs it.
The same specification tells you what is accepted on arrival without any repair at all. On formed non-architectural surfaces, normal colour variations, form joint marks, small surface holes from air bubbles, and minor chips and spalls are accepted; major imperfections, excessive honeycombing and other major defects are not permitted (clause 2.3.4.4.1). Unformed surfaces read the same way, with minor indentations added to the accepted list (clause 2.3.4.4.2).
Two practical consequences:
- A chip is not automatically a defect. Argue the clause, not the appearance.
- Honeycombing is treated differently from a chip. Excessive honeycombing is not in the accepted column at any grade.
The crack thresholds that pull in an engineer
Cracks are where acceptance stops being a visual call. Width is the first screen, direction is the second, and the strand is the third.
The PCI Northeast guidelines set a repair threshold by width. Cracks less than 0.006 in. in width, after detensioning and deemed acceptable, are sealed. Cracks at 0.006 in. or wider are epoxy injected. The same document cites ACI 224 tolerable widths of 0.006 in. for seawater spray with wetting and drying, 0.007 in. for de-icing chemicals, and 0.012 in. for humidity, and notes that fine cracks of 0.004 in. to 0.008 in. can close completely under moist conditions by autogenous healing.
Direction overrides width. Diagonal cracks of any size require evaluation by the engineer. Exposed strand also goes to the engineer. The guideline draws one distinction worth knowing before you call anybody: exposed strand beyond the transfer length can be assumed to have full prestress as though it were never exposed, while prestress lost to a crack or void near the end cannot be restored at that location.
| Observation | Default route |
|---|---|
| Hairline crack under 0.006 in., after detensioning | Seal |
| Crack 0.006 in. or wider | Epoxy injection |
| Diagonal crack, any width | Engineer evaluation before any repair |
| Exposed strand | Engineer evaluation of the engineering effect |
| Pattern of the same defect across several units | Process review, rejection on the table |
Note the qualifier in the width rule: after detensioning and deemed acceptable. A crack measured at the wrong moment in the production cycle is not the crack the threshold is written for.
CPCI’s Architectural Precast Concrete Repair Guide uses a coarser vocabulary for architectural work, defining a crack as fine below 0.01 in. (0.254 mm), medium between 0.01 in. (0.254 mm) and 0.04 in. (1.016 mm), and wide above 0.04 in. (1.016 mm). The guide does not declare which widths are acceptable. It assigns the call: the inspector indicates whether the crack is acceptable, needs remediation, or cannot be repaired. The band tells you what to write on the report. The project documents tell you what the band means.
Appearance is judged against a sample, not against a memory
Architectural units get a second gate. CPCI’s guide notes that mockups of typically 12 in. by 12 in. (305 mm by 305 mm) are shown to the owner as a representative sample, and that the acceptability of repairs should be reviewed during the sample and mockup approval process.
Review repair acceptability at sample approval, months before the first unit ships. A patch that matches the approved sample is a closed item. A patch argued at the trailer against nobody’s sample is an open one.
The guide also puts a scale on the damage it is written for: chips may be as large as 8 in. (203 mm) in diameter by 1 in. (25 mm) deep. That is the size of damage the repair methods address, not a permitted limit. The accepting authority is typically the owner, architect or general contractor, and major repairs follow a contract procedure and are submitted to the owner’s representative or engineer of record.
In Alberta, the repair material has its own qualification
A repair is two decisions. Whether to repair, and what to repair with. Alberta already answers the second one for bridge work.
Transportation and Economic Corridors publishes Specification B391, Bridge Material Testing Specification for Concrete Patching Products, dated September 4, 2025. It rates patching products on strength, bond, absorption, shrinkage, salt scaling, freeze-thaw and chloride resistance, and sets a pass mark: an average rating of 6.0 or greater, no individual rating below 4.0, and only one rating permitted to equal 4.0.
Two of its limits are absolute rather than rated. Freeze-thaw durability factor at 300 cycles shall not be less than 80DF. Maximum moisture expansion shall not exceed the drying shrinkage at 90 days.
That specification governs provincial bridge work, not a private building. Its value elsewhere in Alberta is as a ready-made screen. If a proposed patching product cannot clear a provincial freeze-thaw and salt-scaling screen, asking why is cheap.
Shipping strength is the other number worth carrying. The guide specification requires tests showing a minimum shipping strength of 2500 psi (17 MPa) before units leave the plant, and ties shipping to either an age or a percentage of the specified 28-day strength (clauses 1.4.5.2.1 and 2.3.4.7).
What to do in the twenty minutes the truck is there
Inspection is a sequence, run in this order.
- Count and identify. Mark numbers against the shipping list before anything comes off the trailer.
- Walk the faces that will be visible in service. Those are the faces where appearance criteria apply.
- Measure cracks. Record width, direction and location. Direction decides the route.
- Look at ends and edges. Spalls at bearing ends and at lifting points are the ones that reach capacity.
- Check embeds and openings against the approved drawings. Misplaced embeds are a fit problem, and fit problems do not improve after erection.
- Photograph everything you intend to raise, with a scale in frame.
- Write the non-conformance before you sign. A signature with a verbal reservation attached is a signature.
Damage found after acceptance is a handling question, answered by how the units were stored and rigged. Our notes on dunnage, stacking and the ground under stored units cover storage, and our precast quality control article covers the plant documentation worth requesting before delivery day.
Where this article stops
This article covers acceptance of precast units at delivery and the repair-or-reject decision that follows. It does not price units, specify a product, or set the structural criteria for any particular element.
It does not replace your project documents. The guide specification says plainly that decisions on the need for repair or rejection should be established by the owner, and PCI Northeast describes itself as a guideline rather than a binding standard. Where your specification sets different thresholds, your specification governs.
Structural adequacy of a damaged unit is for the engineer of record. Nothing here authorises accepting a unit with exposed strand, a diagonal crack, or damage at a bearing end without that review.
Bridge and provincial highway work carries its own specification set. Treat the Alberta patching-product specification as a screen, not as the acceptance clause for a building.
Ordering: what the plant needs
Send this with the order, not after the first non-conformance:
| Item | Why it matters |
|---|---|
| Acceptance criteria from your specification | Sets the thresholds the plant builds and inspects to |
| Which faces are architectural, which are not | Decides which appearance clause applies to each face |
| Approved mockup or sample, and repair acceptability agreed at that stage | Closes the patch argument before delivery |
| Named accepting authority on site | Avoids a signature from someone without authority |
| Pre-approved repair procedures you will accept | Converts minor defects into same-day fixes |
| Delivery sequence and unloading method | Separates plant damage from site damage |
| Storage area and bearing surface at the site | Protects units between delivery and erection |
Our plant has supplied and set precast across Alberta for decades, on hundreds of projects where the acceptance conversation happened once, at sample approval, and never again.
Talk to us before your first delivery date. Send the acceptance clauses from your specification and your delivery sequence, and our erection team will confirm inspection points, pre-approved repair procedures and unloading requirements for your units. Scheduling and unloading are handled through delivery and installation; in-service work is handled through maintenance and repair.
FAQ
Can I reject a precast unit for a chip? Usually not on the chip alone. Minor chips and spalls are accepted on formed non-architectural and unformed surfaces under the standard guide specification. A chip becomes grounds for rejection when it impairs functional use or expected life, or when the same chip appears across several units.
Who decides whether a precast repair is acceptable? For a minor defect, any method that does not impair the product may be used. For a major defect, final acceptance is by the owner or the owner’s representative, with the engineer of record involved wherever capacity or durability is touched.
What crack width is acceptable in precast? The project documents decide. As a default, PCI Northeast seals cracks under 0.006 in. after detensioning and epoxy injects cracks of 0.006 in. or wider. Diagonal cracks of any size and any exposed strand go to the engineer regardless of width.
When does responsibility for damage transfer to the site? At acceptance. After acceptance by the customer or the customer’s agent, the manufacturer is not responsible for product damaged by improper jobsite handling. Record and raise non-conformances before signing.
Does the repair material need to be approved? On provincial bridge work in Alberta, patching products are rated and must clear a defined pass mark under Specification B391. On other projects the specification governs, and the provincial screen is a reasonable question to ask of any proposed product.
Sources
- NPCA General Guide Specifications for Precast Concrete Products, National Precast Concrete Association
- Architectural Precast Concrete Repair Guide, Canadian Precast/Prestressed Concrete Institute
- Guidelines for Resolution of Non-Conformances in Precast Concrete Bridge Elements, PCI Northeast
- Specification B391, Bridge Material Testing Specification for Concrete Patching Products, Alberta Transportation and Economic Corridors, September 4, 2025