RTM Home Foundation Requirements in Alberta: The Home Is Certified, the Foundation Is Not

Last updated: November 19, 2026

RTM Home Foundation

The short answer

An RTM home arrives certified. Its foundation does not.

The home is built to a factory certification programme and carries a label. The foundation under it is a separate building permit file, with its own drawings, and in many Alberta jurisdictions its own professional seal. Two authorities, two sets of paper.

Which foundation needs that seal is not a provincial answer. It is a county answer. The counties do not agree.

Two certifications, two authorities

A factory-built home is certified where it is built. A site-built foundation is accepted where it lands.

That split produces the single most common delay we see on RTM files: the buyer has the home’s label number, the serial number and the manufacturer’s drawings, and assumes the package is complete. It is not. The foundation plan is missing, and the foundation plan is the part that may need an engineer.

The County of St. Paul states the scope plainly. A building permit is required for the construction of a manufactured or mobile home, and electrical, gas, plumbing and private sewage disposal permits are separate from it.

What the county permit package asks for

The document list is long and it is specific. The table below is the County of St. Paul list, which is the most fully published of the three we read.

DocumentWho produces it
Development permit application with a detailed site planOwner or agent
Building application formOwner or agent
Builder licence, or owner-builder authorizationBuilder, or the Registrar for owner-builders
New Home Buyer Protection Act registration certificate, or exemption certificateBuilder or warranty provider
Two printed sets, or one PDF, of construction drawings: elevations, floor plans with floor areas for each developed floor, building cross-section, foundation plan, and specifications for engineered elements such as trusses, beams and floor systemsManufacturer, plus the foundation supplier or engineer
Year of manufactureManufacturer label
Serial number and certification number: AMA, CSA, QAI or IntertekManufacturer label
Completed Manufactured Home Information SheetOwner or agent
National Energy Code for Buildings compliance reportBuilder or consultant
National Energy Code Section 9.36 compliance report for houses and small buildings, including additionsBuilder or consultant

Parkland County adds items that catch people out. Radon gas reduction details are required if the home has a full foundation or a heated crawlspace. Any change to approved drawings must be submitted for approval before the change is made. And the development permit, with an approved site plan, comes first.

Which foundations need a professional seal

Three Alberta jurisdictions, three lists. Read the column for your own authority.

Foundation typeCounty of St. PaulParkland CountyTown of Ponoka
Full concrete foundationNo engineer or architect requiredEngineering required for concrete slab foundations supporting a residential structureFoundation to Part 4 or Part 9, National Building Code 2023 Alberta Edition
Concrete frost wall, 4 ft, on a strip footingNo engineer or architect requiredNot listed separatelyNot listed separately
Pier foundation, 4 ft, on a spread footingNo engineer or architect requiredNot listed separatelyNot listed separately
Concrete pile and grade beamEngineer or architect requiredEngineering requiredConcrete pilings require engineering
Concrete pilesEngineer or architect requiredEngineering requiredConcrete pilings require engineering
Screw pilesEngineer or architect requiredPile detail sheet and layout, then pile details and torque values after installationEngineered screw pilings: torque report, fabricated by a CWB certified welder
Preserved wood foundationEngineer or architect requiredEngineering requiredNot listed separately
Slab-on-grade, shallow, larger than 55 m2Engineer or architect requiredNot listed separatelyNot listed separately
Insulated concrete formsEngineering may be needed if no CCMC approval is providedNot listed separatelyNot listed separately
PolycoreNot listed separatelyEngineering requiredNot listed separately
Wood blockingNot listed separatelyNot listed separatelyPermitted per CSA

The three lists disagree, and that is not an error

A full concrete foundation sits in the no-engineer column in St. Paul. A concrete slab supporting a residential structure sits in the engineering-required column in Parkland County. Ponoka does not sort by type at all; it points at Part 4 or Part 9 of the National Building Code, 2023 Alberta Edition, and at CSA-Z240.10.1 for site preparation, foundation and anchorage of mobile homes.

These are three separate authorities having jurisdiction. Each is entitled to set its own submission requirements. There is no provincial table that overrides them.

The operational consequence is short. Do not price an RTM foundation from a neighbouring county’s rules. Pull your own authority’s checklist before you order anything.

Screw piles are the clearest split

Screw piles show the disagreement at its sharpest.

St. Paul requires a professional engineer or registered architect. Parkland County asks for a pile detail sheet and a pile layout up front, then pile details and torque values after installation. Ponoka requires a torque report and requires the piles to be fabricated by a CWB certified welder.

Same product. Three different paper trails. The torque value is the common thread: two of the three want it recorded after the piles are in the ground, which means the number is produced on your site, not in a catalogue.

A relocated home is a different file

A used home moved onto a new site is not treated like a new one.

Parkland County splits the file by label. If the home carries an Alberta Municipal Affairs label and a CSA label, the submission is proof of both labels, the make, model and year built, photographs of the existing condition, and foundation, floor and elevation plans and specifications. Engineering approval may still be required, depending on the proposed foundation and the home’s condition.

If the home has no AMA and CSA label, the file changes shape. An engineer’s letter is required confirming the home is structurally adequate and safe to relocate and place on a new foundation. Testing for mould, mildew or other health hazards may be required. And after the permit is approved and the home is placed, the engineer must return: a site inspection to approve anchorage to the foundation, verification of structural safety, and written verification of the field review submitted to the County.

That last requirement is the one that reaches the foundation supplier. Anchorage has to be inspectable after the home is set.

Ponoka applies the same logic to the label itself. If the home has no CSA number, a full engineer’s report is required to certify the structure. An AMA label number is required for homes built before December 16, 2019.

Age triggers an inspection

The County of St. Paul requires the year of manufacture, and homes over 10 years old need a Safety Codes Officer inspection report before occupancy.

Plan for it in the schedule, not in the budget conversation afterwards.

Numbers you will be asked for

Ponoka publishes the dimensional requirements most owners get wrong. They apply to what is built around the home, and they are the reason a foundation drawing and a deck drawing usually arrive together.

ItemRequirement
Crawlspace clearance, grade to bottom of floor joists24 in minimum
Crawlspace ventilationAt least 1 sq ft per 50 sq ft of crawlspace area
Crawlspace access hatch500 mm x 700 mm minimum (20 in x 28 in)
Crawlspace ground slope2 percent minimum, for drainage
Crawlspace ground cover0.1 mm polyethylene
Stair rise125 mm to 200 mm (5 in to 8 in)
Stair run or tread255 mm to 355 mm (10 in to 14 in)
Handrail height865 mm to 1,070 mm (34 in to 42 in), required on exterior stairs with more than 3 risers
Guard height, landing 600 mm to 1,800 mm above grade900 mm (36 in)
Guard height, landing more than 1,800 mm above grade1,070 mm (42 in)
Bedroom window, relocated home380 mm minimum opening, 0.35 m2 minimum area

Parkland County adds one more threshold worth knowing before the drawings are drafted: engineering is required for tall walls exceeding 12 feet.

The drawings have to say more than you expect

Parkland County’s checklist reaches well past the foundation plan. Floor plans must show the dimensions and purpose of every room, the location and description of all fixed equipment such as sinks and bathtubs, and the location of all smoke and carbon monoxide alarms. Elevations are required from all four sides with exterior cladding details. Cross sections must show labelled rooms, roof pitch, and wall, floor and truss details. The drawings must also carry the location, height and size of all walls, partitions, doorways, windows and other openings, stud size and spacing, lintel sizes over windows and doors, and stair details.

The County of St. Paul allows one piece of slack worth knowing: layouts can be onsite at framing stage. It also requires engineering for hydronic in-floor heating plans and geothermal heating plans, which is a decision to make before the crawlspace is designed, not after.

Where precast foundation walls fit

A precast foundation wall is a plant product. It ships with plant drawings.

That matters on an RTM file for one reason. The permit package needs a foundation plan either way, and the plant produces one as part of the order. Our design and engineering and delivery and installation scope covers the drawings, the set and the hand-off, which is the part of the file a manufacturer’s home drawings do not cover.

Whether your authority classifies a precast wall as a full concrete foundation, or asks for a seal on it, is the authority’s call, not ours. Ask the question in writing before you order. The answer changes nothing about what the plant supplies; it changes who signs the drawing you submit.

If you are still choosing between systems, the three-way comparison of solid precast, cast-in-place and insulated composite walls sets out the trade-offs. If you want the chain of responsibility for seals and shop drawings, that is covered separately in who owns the variance.

Precast walls for residential work sit in our residential precast scope.

The sequence is foundation first

The home moves once. The foundation has to be finished, inspected and ready when it does.

That ordering is the reason RTM schedules fail at the foundation, not at the home. The manufacturer has a build slot. The mover has a window. The foundation sits between them, and it needs a permit, drawings, possibly a seal, possibly a torque report after installation, and an inspection.

On rural and acreage lots the set itself needs planning too. Crane reach, ground conditions and approach are a separate job, covered in crane access on a rural yard.

Where this article stops

This article covers the foundation permit package for a factory-built or relocated home in Alberta, and the engineering thresholds three jurisdictions publish.

It does not set your authority’s requirements. Three counties were read for this article and they differ on the central question. Yours may differ again.

It does not cover the private sewage, electrical, gas or plumbing permits, which are separate files. It does not cover the home’s own certification, which is the manufacturer’s responsibility. It does not state warranty coverage periods or exemptions; the county asks for a registration or exemption certificate, and Alberta Municipal Affairs issues those. The County of St. Paul lists 1-866-421-6929 for those questions.

Geotechnical conditions are not addressed here. Bearing capacity, frost and groundwater on your specific lot are an engineer’s determination.

Ordering: what the plant needs

Send these and we can start drawings:

  • Site address and legal land description, plus the municipality or county that issues the permit.
  • The home manufacturer’s foundation loading plan or set-out drawing, with overall dimensions and bearing point locations.
  • Confirmation of the foundation type your authority will accept, and whether it requires a seal.
  • Required wall height, and whether a crawlspace or full basement is intended.
  • Geotechnical report if one exists; if not, say so.
  • Site access notes: approach, overhead lines, ground conditions, and whether a crane can set up.
  • Target date the home is scheduled to move.

FAQ

Does an RTM home foundation need an engineer in Alberta? It depends on your authority and the foundation type. The County of St. Paul does not require an engineer or architect for a full concrete foundation, a 4 ft concrete frost wall on a strip footing, or a 4 ft pier foundation on a spread footing, but does require one for concrete piles, concrete pile and grade beam, screw piles, preserved wood foundations, and shallow slab-on-grade larger than 55 m2. Parkland County requires engineering for concrete slab foundations supporting a residential structure. Confirm with your own permit issuer.

Can I put an RTM home on screw piles? Yes, in the jurisdictions reviewed, but the paper differs. One requires a professional engineer, one requires a detail sheet and layout followed by torque values after installation, and one requires a torque report plus fabrication by a CWB certified welder.

What if the home has no CSA label? Ponoka requires a full engineer’s report to certify the structure. Parkland County requires an engineer’s letter confirming the home is structurally adequate and safe to relocate, and requires the engineer to inspect and approve the anchorage after the home is placed, with written verification of that field review.

Does the age of the home matter? Yes. The County of St. Paul requires a Safety Codes Officer inspection report before occupancy for homes over 10 years old.

Which comes first, the development permit or the building permit? The development permit, with an approved site plan, is listed first on both county checklists reviewed. The building permit file is assembled around it.

Get the foundation drawings moving

Send the manufacturer’s set-out drawing and your site address, and we will tell you what the plant needs and what your permit package is still missing. Start with our residential precast scope and send the drawing.

Sources: Parkland County, Checklist for a Manufactured Home or Single Mobile Home | County of St. Paul, Manufactured and Mobile Homes | Town of Ponoka, Mobile and Manufactured Home Requirements Checklist