Elevator Pit Requirements in Alberta: The Device Sets the Inside, and a Second Permit Accepts It

Last updated: November 4, 2026

Elevator Pit Requirements in Alberta

An elevator pit is a concrete box with a short list of hard requirements and a separate inspector. The concrete scope does not set its inside dimensions. The elevating device does. And the body that accepts the finished pit is not the building inspector.

That split is the whole problem. A pit gets set on a building permit, then fails a provincial elevating device inspection over a ladder rung spacing, a missing drain, or a sump cover sitting proud of the floor. The structure was never the issue. The fit-out items were.

What an elevator pit is, in precast terms

The pit is the bottom of the hoistway. It sits below the lowest landing. It carries buffer and guide-rail reactions. It resists ground water from outside and keeps water out of the hoistway inside.

As a precast product it is a four-sided box with a floor, cast as a unit or as panels with a cast floor. The attraction is the same as every other buried precast product: made under cover, cured under control, set in one lift. The pit is watertight before the hole has been open a week.

We quote these as structures, not shapes. The geometry is an input from the elevator supplier. The precast scope is the box, the embeds, the openings and the lifting.

The code in force in Alberta

Alberta does not write its own elevator code. It adopts one.

The code declared in force is ASME A17.1-2019/CSA B44:19. Alberta STANDATA 19-EDI-006, issued November 2022, states that unless noted otherwise all code references are to that edition. Adoption runs through the Elevating Devices Codes Regulation under the Safety Codes Act.

The adopted list is longer than the elevator code alone. It also includes ASME A17.6-2022, ASME A17.7/CSA B44.7-07 (R2021), CSA B44.1-2023/ASME A17.5-2023, CSA B355-2019 for platform lifts and stair lifts, CAN/CSA-B311-02 (R2018) for manlifts, and CAN/CSA-Z185-2023 for personnel hoists.

Two consequences matter to a concrete scope. The device class decides which standard governs, and a platform lift under CSA B355 is not an elevator under CSA B44. And building code requirements can be varied independently. Alberta STANDATA 19-BCV-003(REV1) / 19-EDB-001 does that: where a passenger elevator replaces a barrier-free lift, the car need not accommodate a stretcher, which NBC(AE) 2019 Sentence 3.5.4.1.(1) otherwise requires at 2 010 mm long by 610 mm wide in the prone position. The conditions are vertical travel of 7 000 mm or less and car dimensions no less than Table 1 of CSA B355. That 7 000 mm threshold also decides whether firefighters’ emergency operation elements are required, and a pit drain requirement hangs off it.

The pit dimensions are not yours to set

Pit depth is a device output. It follows from buffer selection, compensation and the running clearances the device needs below the lowest landing. The elevator supplier issues a layout drawing. That drawing is the dimension source for the pit.

The sequence is fixed, and it runs opposite to the way most schedules are drawn. The device is selected. The supplier issues a layout. The layout is authenticated by a registered engineering professional and submitted with the permit application. Only then is the pit a known box.

A pit ordered before the device is a guess, and the error surfaces as a depth change after the hole is dug. We quote from a supplier layout, not from a floor plan with a shaft outline and a note saying “elevator by others.”

Ground water is the pit’s first requirement

The pit has to stay dry. Alberta’s elevating device pre-inspection checklist, published by the Alberta Elevating Devices and Amusement Rides Safety Association (AEDARSA), puts it as a flat requirement: permanent means shall be provided to prevent the accumulation of ground water in the pit.

That is a performance requirement with no prescribed detail. The detail is yours to design and prove. On a precast pit the usual combination is a watertight box, sealed joints, a drainage layer and a positive discharge path, coordinated against the plumbing rules below.

The checklist’s pit items are specific:

Pit itemRequirement as written
Ground waterPermanent means shall be provided to prevent the accumulation of ground water in the pit
Pit drainPit drains shall be designed with a positive means to prevent water, gases, and odors from entering the hoistway
Sump coverSumps and sump pumps installed in elevator pits shall be covered securely; the cover shall be secured and level with the pit floor
Sump powerSump pumps installed in pits shall have a dedicated single supply receptacle
FEO drainInstall a pit drain, if the elevator is provided with firefighter’s emergency operation, with pump rated at 3 000 gals/hr
ReceptaclesEach pit receptacle shall be a GFCI type, except for sump pumps
LightingPermanent lighting shall be installed in the pit, with an illumination of not less than 100 lux at the pit floor
Light guardThe pit light shall be provided with a guard
Switch locationThe light switch shall be installed such that it is easily accessible from the bottom landing door

Read the sump cover line twice. “Level with the pit floor” is a tolerance, and on a precast pit it is a recess that has to be cast, not chased later. Casting a recess is cheap. Cutting one is not.

The drain, the sump, and the clause that had to be varied

This is the item most often missed, because it is not in the elevator code at all. It is plumbing.

Clause 2.4.3.6(1)(a) of Division B of the National Plumbing Code of Canada would not permit a sump located inside the elevator pit. Alberta issued a plumbing safety variance to allow it. VAR-P09.01 [Rev 1], dated November 2014, varies that clause to allow sumps to be located inside the elevator pit when a drain is provided.

The variance is narrow. It addresses only clause 2.4.3.6(1)(a). The companion requirement in clause 2.4.3.6(1)(b) still stands: the drain pipe that connects the sump to the drainage system shall have a backwater valve. Conditions apply. Drainage installations must follow the manufacturer’s instructions and the plumbing code, and sump equipment work must be under the direct supervision of an elevator certified journeyman, present on site.

Oil interceptors are the other half. Hydraulic devices put oil in the pit, and the variance notes plainly that oil interceptors may require external installation, because space in the shaft makes an internal one impractical.

Both facts land on the precast scope as embeds. A drain outlet, a sump recess, and sleeves for the discharge line and an external interceptor are cast-in items, decided before the pour. The load class and discharge discipline in our precast trench drain article is the same thinking in a different box.

Pit access: the ladder is a dimensioned assembly

The pit ladder is not generic. The checklist dimensions it.

Ladder itemRequirement as written
Horizontal positionShall be installed within 1 000 mm horizontally from the unlocking means of the bottom landing door
Vertical extentShall extend from the pit floor to a point 1 200 mm above the bottom landing door sill
WidthMinimum 400 mm wide, less when obstructions are encountered, and as wide as space available; not less than 225 mm
Rung spacingRungs, cleats or steps shall be spaced 300 mm on centre
Rung clearanceNot less than 115 mm
Fixing and materialShall be fixed in place and made of non-combustible material
ObstructionsShall be installed to avoid any obstructions within the rungs, cleats or steps

Two of those are wall conditions, so they are precast conditions. The ladder has to be fixed, which means anchors or cast-in inserts in a known location. And it has to clear obstructions through its full height: no pipe, no conduit, no projecting embed in the ladder zone. Mark that zone on the shop drawing and keep it clear.

Pit access door and hoistway surfaces

Where a separate pit access door is used, it is self-locking and self-closing, its key security code is designated Group 1 Security, it carries a vision panel where applicable, and it meets the applicable building code fire rating.

The hoistway enclosure has its own list, and parts of it are concrete work. All holes, recesses and gaps in the enclosure and ceiling have to be eliminated. Projections, setbacks or recesses greater than 100 mm have to be bevelled at 75 degrees to the horizontal. The enclosure meets the building code fire rating. Pipes and ducts carrying gases, vapours or liquids not used with the elevator are removed, as is unrelated wiring.

Bevels on a precast panel are formwork. They cost almost nothing on the drawing, and a grinder and a day when they are not.

The second permit

The elevating device needs its own permit. In Alberta that application is form EDA/045/rev2025, Construction and Major Alteration Permit Application, and one application is used for each elevating device.

Permit elementWhat the application requires
DrawingsA list of all authenticated drawings and supporting documents submitted by registered engineering professionals
AuthenticationCertification under Alberta Registered Engineering Professional Authentication and Permit to Practice
ConformanceA list of Certificates of Conformance issued by an AECO where compliance uses ASME A17.7/CSA B44.7; outdated certificates will be rejected
Device dataClass and type, number of floors, number of openings, capacity, emergency power operation, firefighters’ emergency operation, machine and controller make, model and serial number
VariancesAny variance request is submitted with the application
FeesThe application fee must be paid before an inspection is booked
ChangesIf plans change after registration, updated plans and an itemized list of all changes must be resubmitted

The last line is the schedule risk. Changes discovered at inspection that are not in the registered scope of work require resubmission and may end the inspection. A pit depth changed in the field is exactly that kind of change.

Operation is a third step. A Permit of Operation is required before a device is operated, and new devices get a first in-service inspection within twelve months of release for public operation, then on a cycle: every two years for passenger elevators, freight elevators and dumbwaiters, yearly for escalators, moving walks, barrier-free lifts and manlifts.

Where the concrete scope usually fails

Five items, in the order we see them. Wrong pit depth, because it was built from an architectural shaft outline instead of a device layout. No cast sump recess, so the cover cannot sit level. No sleeve for the sump discharge or an external interceptor. Ladder anchors missing or landing in front of a conduit. A hoistway projection over 100 mm never bevelled.

None are structural. All are drawing items, which is why we settle them before casting, and why the discipline in our erection sequencing guide for GCs applies here. Our embed and tolerance checks are described in our quality control article.

Where this article stops

This article covers the pit and the building-side items that an elevating device inspection checks. It does not cover the device.

It does not select buffers, size a hydraulic jack, specify a controller or lay out machine room equipment. It does not give pit depths; those come from the device layout. It does not reproduce ASME A17.1/CSA B44 clause text, which is a purchased standard. It does not cover machine room construction beyond noting that the room has its own checklist: 2 134 mm minimum headroom, permanent lighting at not less than 200 lux at floor level, a 450 mm clear horizontal path around equipment, and 1 000 mm clear in front of controllers and disconnects.

It is also not the authority having jurisdiction. The accepting body for the device is AEDARSA or another accredited agency. Confirm the current edition, variances and fees with them before you submit.

Ordering: what the plant needs

Send these and we can price and schedule a precast pit:

  • The elevator supplier’s layout drawing, with pit plan dimensions and pit depth.
  • Device class and type, capacity, and whether firefighters’ emergency operation is provided.
  • Finished floor elevation at the bottom landing, and the pit floor elevation.
  • Groundwater information: geotechnical report, water table, and any existing drainage layer or discharge path.
  • Drainage intent: sump inside the pit with a drain, external interceptor, or both, with sleeve sizes and locations.
  • Ladder location relative to the bottom landing door unlocking means, and the fixing type.
  • Hoistway enclosure fire rating and any required bevels or setbacks.
  • Crane access and the pick radius at the shaft location.

With a layout in hand we quote the box, the embeds and the lift together. Without one we are quoting a guess. Our solutions overview lists the sectors we build these for, and the plant gives lead time once the layout is registered.

FAQ

Who accepts an elevator pit in Alberta? The elevating device is accepted under the Elevating Devices Codes Regulation, by AEDARSA or another accredited agency, against ASME A17.1-2019/CSA B44:19. The building permit does not cover it.

Can a sump go inside an elevator pit? Yes, when a drain is provided. Alberta STANDATA VAR-P09.01 [Rev 1] varies Clause 2.4.3.6(1)(a) of Division B of the National Plumbing Code to allow it. The drain pipe connecting the sump to the drainage system still requires a backwater valve.

Does the pit need a drain? A pit drain is required where the elevator has firefighters’ emergency operation, with a pump rated at 3 000 gals/hr. Separately, permanent means to prevent accumulation of ground water is required in every pit.

How deep does an elevator pit have to be? There is no general number. Depth follows the device, from the supplier’s layout drawing. Order the pit from that drawing.

What are the pit ladder dimensions? Within 1 000 mm horizontally of the bottom landing door unlocking means, from the pit floor to 1 200 mm above the sill, minimum 400 mm wide, rungs at 300 mm on centre, fixed and non-combustible. Full list in the ladder table above.

How much lighting does a pit need? Not less than 100 lux at the pit floor, permanent, with a guard and an accessible switch.